Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/nailbendersgroup/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the stm_post_type domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/nailbendersgroup/public_html/wp-includes/functions.php on line 6114
AFGHAN NATIONAL ARMY (ANA) SECURITY UPGRADE, GARDAZ, PAKTYA, AFGHANISTAN – Nailbendersgroup

AFGHAN NATIONAL ARMY (ANA) SECURITY UPGRADE, GARDAZ, PAKTYA, AFGHANISTAN

AFGHAN NATIONAL ARMY (ANA) SECURITY UPGRADE, GARDAZ, PAKTYA, AFGHANISTAN

the project consists of the design and construction of security upgrades at Camp under, Gardez City,
Paktya Province. e project is defined as the design, material, labor and equipment to demolish existing fence and Hesco wall and construct new perimeter wall, mounted and dismounted fighting positions, renovate guard towers, improve interior road drainage and repair interior perimeter patrol road. e work within this contract meet in accordance with current U.S. design and International Building Codes (IBC), Life Safety Codes (NFPA-101), Force Protection and security standards.

 

Following were the key deliverables of the projects:

  1. Construction of approximately 2758LM of RCC wall with Native Stone Masonry Veneer and Y-channel concertina razor wire, Demolition of 2758LM of existing barbed wire fence and 700LM of existing Hesco barriers.
  2. Renovate 14 guard towers. Install ceiling fans and unit heaters in each; demolition of existing stairs and install stairs with landings at each.
  3. Pavement of 5km of existing interior perimeter road with Asphaltic Macadam. Grade road to allow for proper drainage and vehicle exit onto mounted fighting positions.
  4. Construction of eleven (11) perimeter wall fighting positions, construction of dismounted fighting positions (DFPs) and mounted fighting positions (MFPs), which the DFP/MFPs include the force protection elements to include, but not limited to the barbed wire, concertino wire, supports, and concrete cap.
    e fighting position behind the wall consist of HESCO Barriers and shooter platform with steps.
Client
USACE – PRO BUILT
Year
2011
Contract No
W5J9JE-10-D0008-0013